Reviewed the Estuary Plan, previous studies and the latest information from the Environment Agency, including data on ground levels, flood defence condition and water levels across the estuary.

PROJECTS
Civil Engineering
Alde & Ore Estuary
Alde & Ore Estuary Trust
Alde & Ore Community Partnership
Environment Agency
2026 ongoing
Planned completion 2031-32

The Alde & Ore Estuary is protected by a network of embankments that help reduce the risk of flooding to homes, businesses, farmland, infrastructure and important habitats. These defences are under increasing pressure from rising sea levels, more frequent storm events and the natural ageing of the embankments.
The Alde & Ore Estuary Plan sets out a long-term approach to managing flood risk. While we continue to work towards delivering the full programme of improvements, we are now launching a coordinated five-year maintenance programme to help sustain the existing flood defences across the entire estuary.
East Suffolk Water Management Board, the Alde & Ore Estuary Trust, the Alde & Ore Community Partnership and the Environment Agency have partnered to deliver a systematic rolling programme helping to improve the resilience of the estuary’s flood defences year on year. The partnership are committed to invest at least £500,000 each year over the next five years.

Our original plan was to begin raising embankments in the Upper Estuary before progressing to the Lower Estuary as additional funding became available. However, updated flood modelling showed that carrying out works in only part of the estuary could unintentionally increase flood risk elsewhere. As a result, permission for that approach was not granted.
Rather than delay work while funding for the full capital programme is secured, we have reviewed alternative options that allow us to begin protecting the estuary now.
The new maintenance programme focuses on sustaining flood defences across all flood cells in the estuary, maintaining the current level of flood protection while longer-term improvement and adaptation options continue to be developed. This approach aligns with the Estuary Plan and can be delivered more quickly, with minimal additional permissions required.
The updated modelling also confirmed that proposed works at Snape Maltings (Flood Cell 06) would not increase flood risk elsewhere. Britten Pears Arts Ltd is therefore progressing privately funded works within this flood cell.

The five-year maintenance programme will help preserve the estuary’s existing flood defences while creating opportunities to strengthen their resilience over time.
The programme will:



Reviewed the Estuary Plan, previous studies and the latest information from the Environment Agency, including data on ground levels, flood defence condition and water levels across the estuary.
Developed and tested methods for identifying maintenance needs across the whole estuary using available data. Carried out site visits and inspections throughout the estuary, including GPS surveys and photographs, to verify and improve the accuracy of project data.
Detailed investigations around the Estuary undertaken. Provided support to the Environment Agency to help identify urgent maintenance priorities and requests for funding. Work also continues to refine the assessment methods being used across the project.
Develop and test methods for assessing the condition and reliability of flood defence assets, alongside quantifying the potential impacts of flooding. This will create an initial “long-list” of possible maintenance and improvement activities across the estuary.
Carry out targeted site surveys to confirm maintenance requirements. Develop and test methods for assessing the costs and benefits of different interventions. Prioritise activities from the “long-list” to produce a recommended programme of works for the current five-year management period, involving the opportunity for discussions with the estuary community through the AOCP.
Completing planning activities such as securing any consents or licences required, design works, access arrangements and enabling works.
Works are planned to commence across the Estuary.