Exeter Drain Improvement Project
Work is continuing across the Exeter Drain Improvement Project, with activity progressing across all three main areas of the scheme.
At Mulberry Way, Matmore Close and Clay Lake, all the new pipework and inspection chambers for the upgrades to Culverts 3 and 4 have now been installed. Work has moved on to building new concrete headwalls at the ends of the pipes. Temporary supports have been put in place to hold back the surrounding ground and create a safe working area while the foundations and headwalls are constructed. Work in this area is expected to continue into early December.
At Maple Grove and Cley Hall Drive, progress has been slower than anticipated due to challenging ground conditions as work has moved north towards Albert Street. This has made it more time-consuming to install the temporary supports needed to create a safe working area. Work on Culvert 1 is now expected to continue into December, followed by reinstatement of the affected areas.
Along the open channel, the first section of permanent steel piling in the northern section has been completed. Work is now moving on to preparing the area for new reinforced concrete sections, which are expected to begin in mid-November. The concrete will be installed in sections of around 30 metres at a time to help manage the work safely and maintain the quality of the finished structure.
Work will continue across the different areas of the project over the coming months, with construction currently expected to run through to March 2027.