Member Boards

Associate Boards

Upper Thurne Integrated Drainage Improvement Project

Martham Pumping Station

Boots Services Icon Blue

Services

Civil Engineering

Location Icon Blue

Location

Martham
Norfolk

Partner Icon Blue

Partners

Bam Nuttall
Jacobs
Turner & Townsend

Completion Clipboard Icon Blue

Start & Completion

March 2026 – Ongoing

Water Vole nibbling on vegitation at waters edge

Enabling Works and Environmental Considerations

To facilitate the pumping station construction, we undertake enabling works, including ecological mitigation in advance.

  • Vegetation clearance and management – removing or trimming plants, trees and vegetation to discourage bird nesting and manage reptile habitat.
  • Water vole mitigation – carrying out surveys, vegetation management and mitigation alongside measures such as habitat enhancement, exclusion zones and careful timing of works to protect this legally protected species.
  • Bat surveys – undertake bat roost surveys in the existing buildings and surrounding habitats and plan / programme works ensuring compliance with regulations.
  • Access improvements – strengthening, widening, or creating access routes so vehicles, machinery, and personnel can safely reach the site.
  • Service and utility diversions – identifying existing underground or overhead utilities and rerouting or safeguarding them to avoid disruption or damage during construction.
Upper Thurne ID Project Map

Upper Thurne Overview

The Upper Thurne Integrated Drainage Improvement Project will replace or refurbish 11 of the 14 pumping stations within the River Thurne catchment in the Norfolk Broads at Horsey, St Benets, Martham, Potter Heigham, Brograve, Stubb, Catfield, Horse Fen, Repps Staithe, Somerton South, and Thurne.

The current submersible canister pumping stations were typically built in the 1950’s with some housed within far older foundations dating back to the 19th Century. Despite ongoing maintenance to sustain their operation all have significantly exceeded their design life and are unsuitable for further refurbishment.

Collectively the 14 pumping stations protect over 6300 hectares of Broads Internal Drainage Board districts including nationally and internationally designated habitat, 708 properties, local communities, tourism and infrastructure.

Each site features unique challenges with a mosaic of designated habitats including Sites of Special Scientific Interest (SSSI’s), Special Area of Conservation (SAC’s), Special Protection Area (SPA’s), National Nature Reserve (NNR’s) and Ramsar designations as well as significant variations in ground conditions.

The existing pumping stations are generally built in existing raised flood defences, within or adjacent to historic infrastructure.

The presence of active boat yards, staithes, moorings and other tourism such as the National Trust Horsey Wind Pump present a unique set of challenges to the project.

Broads IDB at Brograve Aerial image of flooding due to embankment overtopping in 2023

Benefits

The Upper Thurne Integrated Drainage Improvement Project will bring significant benefits to both the environment and local communities:

  • Improved flood resilience for over 700 homes, vital tourism assets, and local infrastructure
  • Safeguarding nationally important habitats, ensuring long-term protection for wetlands that support rare wildlife and biodiversity
  • Sustainable drainage systems that reduce maintenance requirements and extend the working life of critical infrastructure
  • Long-term climate resilience, by replacing ageing assets with modern, efficient pumping technology